---
title: "Short-circuit withstand: the cable check everyone skips"
description: "A cable that passes current rating and volt drop can still fail under fault. The adiabatic check, the right k value, and why discrimination delays cost copper."
date: "2026-03-23"
author: "Divakar B"
source: "https://energycalchq.com/blog/cable-short-circuit-withstand"
license: "© 2026 Divakar B. Quote with attribution to https://energycalchq.com/blog/cable-short-circuit-withstand"
---

Cable sizing usually stops when two conditions are satisfied: the cable carries
the load current after derating, and the volt drop is inside the limit. Both are
about normal operation. Neither says anything about the two-tenths of a second
when a fault is on the system and the cable is carrying twenty thousand amperes.

That is a separate check, it is genuinely capable of picking a larger cable than
either of the other two, and it is the one most often left out — including by
software that produces a very confident-looking schedule.

## What actually happens during a fault

For the fraction of a second before the breaker opens, the fault current flows
through the cable. It is far too brief for any of that heat to escape into the
surroundings — all of it stays in the conductor and raises its temperature
directly.

If the conductor gets hot enough, the insulation is damaged. It may not fail
that day. PVC that has been cooked once is brittle, and the circuit that tripped
cleanly in March becomes an earth fault in September.

The condition to satisfy:

```
k² S² ≥ I² t
```

or, rearranged into the form you actually use:

```
S ≥ √(I² t) / k
```

with S the cross-section in mm², I the fault current in amperes, t the total
clearing time in seconds, and k a constant for the conductor and insulation.

## The k value trips people up

The same conductor has two different k values depending on the job it is doing,
and using the wrong one is the commonest mistake in this calculation.

| Conductor | Phase conductor | Protective conductor |
|---|---|---|
| Copper, PVC | 115 | 143 |
| Copper, XLPE | 143 | 176 |
| Aluminium, PVC | 76 | 95 |
| Aluminium, XLPE | 94 | 116 |

Why the difference? A **phase conductor** is already carrying load current when
the fault happens, so it starts at its operating temperature — 70 °C for PVC.
A **protective conductor** normally carries nothing, so it starts at ambient,
around 30 °C. The protective conductor has 40 °C more headroom before it reaches
the same damage temperature, and that extra margin is what the larger k
expresses.

Use the phase-conductor column for the cable you are sizing here. Use the
protective-conductor column in the [earthing conductor
calculator](/tools/earthing-conductor), which is a different calculation with
the same equation.

## The clearing time is the expensive input

Because cross-section scales with the square root of time, a slow device is
punished hard.

![Curve of required copper cross-section against clearing time for a 20 kA fault](/blog/short-circuit-withstand-curve.svg "The same fault current. Only the protective device's clearing time differs, and it moves the answer from 70 mm² to 150 mm².")

Worked through at 20 kA on a PVC-insulated copper cable:

```
Clearing in 0.1 s:
  S ≥ √(20,000² × 0.1) / 115 = 6,325 / 115 = 55.0 mm²   → fit 70 mm²

Clearing in 0.6 s:
  S ≥ √(20,000² × 0.6) / 115 = 15,492 / 115 = 134.7 mm² → fit 150 mm²
```

Two frame sizes of copper, bought entirely with time.

This is the hidden cost of discrimination. Every deliberate delay you set on an
upstream device — so that the downstream one trips first and only the faulty
circuit is lost — has to be paid for in the withstand rating of everything
upstream of it. Discrimination is usually worth having. It is not free, and the
cable schedule is where the bill arrives.

Get the time from the **actual device curve at the actual fault current**, not
from a table of maximum permitted disconnection times. Those tables are about
shock protection, which is a different requirement with a different purpose.

## Where current-limiting devices change the picture

A current-limiting MCCB or an HRC fuse opens so fast that it cuts the fault
before the first peak is reached. The cable never sees the prospective current
at all.

For these, the calculation above is far too pessimistic. Use the device's
published **let-through energy** — the I²t value in A²s from its datasheet — and
check it directly against the cable:

```
k² S² ≥ let-through I²t
```

A 100 A current-limiting MCCB might let through 0.15 × 10⁶ A²s on a 20 kA
fault. For 70 mm² copper PVC, `k²S² = 115² × 70² = 64.8 × 10⁶` — a very
comfortable margin. On high fault-level systems this is often the only
economical way to protect a cable, and it is why fuses persist on large feeders
long after breakers took over everywhere else.

## Where the fault current comes from

You need a fault current at the point being protected, and it is not one number
for the whole installation.

Start at the transformer: the [transformer sizing
calculator](/tools/transformer-sizing) gives the terminal fault level from the
kVA and impedance. Then remember that impedance accumulates down the system —
every metre of cable reduces the fault current further from the source. The
[short circuit current calculator](/tools/short-circuit-current) builds that up
properly, adding the cable resistance and reactance to the transformer
impedance and reporting the fault at the point you care about rather than at
the terminals.

That gives two checks, not one:

- **At the origin of the cable**, where the fault current is highest. This is
  the case for conductor damage.
- **At the far end**, where the fault current is *lowest*. This matters because
  a fault there must still be large enough to operate the protective device
  quickly. A long, thin cable can produce a fault current so low that the
  breaker's magnetic element never picks up and the cable is protected only by
  the much slower thermal element — at which point the withstand calculation has
  to be redone at that much longer time, and it usually fails.

The second case is the one that catches people on long submains, and it is the
argument for checking the earth fault loop impedance rather than assuming.

## Cables in parallel

Where a feeder is made up of two or more cables per phase, the fault current
divides between them — but only if they are genuinely identical. Same size, same
length, same route, same installation method. Then each cable is checked against
its own share, and the requirement per cable falls accordingly.

Depart from that in any way and the assumption collapses. A parallel set where
one run is noticeably shorter has a lower impedance on that path, so it takes
more than its share of both load and fault current. The short cable overheats
while the long one loafs, and the withstand calculation you did on an equal
split was never true. If the routes cannot be made equal, size every cable in
the set for the worst-case share rather than the average.

## Where this sits in the sequence

Short-circuit withstand is step six of the [six-step
sequence](/blog/how-to-size-a-cable-correctly), and in that worked example — a
45 kW motor with a compliant 50 mm² by every other measure — it is the step that
drove the answer to 70 mm². Current rating and volt drop both had margin. The
fault check did not.

That is the pattern worth internalising: **each step produces a minimum, and you
install the largest.** A cable schedule that never once got its answer from step
six is a cable schedule where step six was not performed.

## A short checklist

- Fault current from the transformer impedance, reduced for the route to this
  cable.
- Clearing time from the device curve at that current — including any
  discrimination delay.
- k from the **phase conductor** column, matched to the insulation.
- For current-limiting devices, use published let-through energy instead.
- Check the far end as well as the origin, and confirm the device still operates
  magnetically on a fault there.
- Take the largest size produced by all the checks, then confirm it still passes
  volt drop with the [voltage drop calculator](/tools/voltage-drop) — a bigger
  cable never fails that, but the schedule should record the final size against
  every criterion.
